Sector - Commercial

Scope - Strip-out and Refurbishment

Location - Gillingham

Duration - 2 months

Year - July 2023

Cost - £100K

Gillingham Football Club, Executive Boxes

Strip-out & Refurbishment of 5.no Executive Boxes at Priestfield Stadium, Gillingham

01

Context & Planning

Having worked with Gillingham Football Club on several previous occasions, Bauvill were approached to design and deliver an upgrade project of the club’s corporate executive boxes. These boxes are a vital part of the commercial hospitality offering at GFC, often sold for an entire season or match-by-match basis, meaning we had to ensure the final product exceeded customer expectation. The existing boxes were dated and originally fitted out over a decade ago, which meant a full strip out and make good was required before we could proceed with the improvement project. Added to the challenge was the requirement for the boxes to be complete before the start of the 23/24 season, giving us a short window of opportunity to complete the project with a deadline looming.

02

Major Works

Once the boxes had been fully stripped and all walls, ceilings and floors were made good, the initial task was implementing the design of the kitchen areas and cabinetry which form a focal point of each box. The idea was to give this area a modern sleek look whilst delivering on operational requirements which would be robust enough to last for years to come. Equally important was the fit out of new toilets which included flooring, sanitary ware and decorations. The full scope of deliverables included:

  • Demolition; removing carpet, plasterboard, ensuite, removing of services

  • 1st fix M&E; new feeds and waste to toilet and kitchenette, new wiring for lighting

  • 1st fix drylining

  • 2nd fix drylining

  • Plastering of new walls

  • Carpentry works; doors and skirtings

  • 1st coat decorations

  • Install of toilet and sinks

  • Install of kitchenettes

  • 2nd fix electrical items; lights and sockets

  • Full decorations

  • Carpet installations

  • Mastic works

  • Manifestation

  • Builders clean

03

Completion

The final boxes were complete and handed over before the club’s first friendly fixture of the 23/24 season, ahead of schedule whilst delivering over and above all design and specified requirements. The club’s new owners were delighted with the final product which has led to discussions about further improvement projects around Priestfield Stadium which Bauvill will undertake. We look forward to working with GFC on the club’s regeneration project, both on and off the pitch through a partnership that we hope will continue for years to come.

Contact

Contact us today. Our team is only too happy to answer all your questions

enquiries@bauvill.co.uk

Similar Projects

Gillingham FC, First Team Facilities

Brook View, Farmborough

Trinity Foyer, Maidstone

A modern construction company with traditional values. Excellence within the Healthcare, Commercial, Education and Facilities sectors.

Unit 52-54, Riverside Estate, Sir Thomas Longley Rd, Rochester, ME2 4DP
Constructionline Gold Member Badge
SafeContractor Approved Badge
SSIP Registered Member Badge